The problem
Company goals were tracked in another OKR tracker, and it wasn't flexible enough for the way leadership wanted to manage them. They wanted the C-suite to set the direction and every department to set objectives that rolled up to it.
Constraints
- Three audiences. The C-suite, department heads, and the people reporting on key results each needed something different.
- Visible to everyone. The whole company could see the whole tracker.
- Another team's project. Strategic Operations owned it. I was brought in as the company's Notion expert.
My part
- Designed all the formulas.
- Reworked the database that Strategic Operations had started, to make it more functional.
- Built the three dashboards.
- Taught the team how to build the structure and create the relations, and took on the complex database and formula work when they got stuck.
Three levels, one owner each
Strategic initiatives sit at the top and belong to the C-suite. Objectives belong to department heads, and each one relates to an initiative. Key results belong to selected reporters in each department, and each one relates to an objective.
- Owner
- Departments
- Period
- Due date
- Completion (average of all its key results)
- Status
- Owner
- Departments
- Reporters
- Due date
- Status message
- Completion (average of its key results)
- Status
- Owner
- Percent completed (0–100)
- Status update
- Archived status messages
- Status
From one number to a status
Each key result has a percentage complete. An objective's completion is the average of its key results. An initiative's completion is the average of all the key results beneath it, not an average of the objective averages.
A formula turns each percentage into a status, using the same bands at all three levels.
Check-ins
Reporters checked in monthly and wrote a longer, detailed report each quarter. On a key result, a reporter updates the percentage and a short status message. A button archives the message, so the current update stays short.
A dashboard for each audience
The overview dashboard, shown earlier, is made to be read at a glance. Department heads and reporters get views that go further into their own work.
Decisions
Follow how leadership already thinks. Initiatives, objectives, and key results, with a clear owner at each level.
Let a formula set the status. Status stays consistent, and nobody picks a colour by hand.
Don't average an average. Initiative completion is calculated from every key result, so each one counts equally, however many sit under its objective.
One tracker, three views. Everyone works from the same data and starts from the dashboard built for them.
A light monthly rhythm, a deeper quarterly one. Frequent check-ins stay quick, and the detail has a place of its own.
What didn't work, and what I learned
The project stopped during beta testing when its owner left the company, and I left soon after. It was never completed.
I was the person the team called when they got stuck. Bringing the platform expert in while decisions are being made, not after, would have saved rework.
A design that can be reused
A few department heads and members of the C-suite tested the beta. It didn't go into use, so there are no adoption or outcome numbers to show.
What carries over is the design. The structure, the formulas, and the three dashboards can be built in Notion and adapted for any business that wants to set direction and track progress toward it.
What I'd do next time
- Plan for continuity, so the project survives someone leaving.
- Make it a real priority, with the time to finish it.
- Be on the team making the decisions, not only the person it goes to when stuck.